More than 100 builders worked on the construction of such pillbox. The foundation pit digging, mould and armature fitting could be done within 3 days usually. Concrete works continued next 2-3 days. Than the gan and equipment were fixed and camouflage was mounted. The total duration of pillbox construction footed up to one week. The pillbox on the photo situated south-west from Taitzy village.